Summary
Do you need us to bulk update one specific data field for many records in Colleague? If you need a value updated into one field and the number of records that need to be updated is greater than 50, we may be able to help! We will need a minimum of 2 weeks advanced notice of your timeline so we can plan out and test.
Body
Batch Updating a Colleague Data Field
Here is the process that we follow:
- Before you reach out to IT:
- Identify your business need to have a data field bulk updated by ITAS
- Know the field name and mnemonic (the form you see this field on) that needs to have this update
- What is the current value in the field and what would you like it replaced with
- Know the record set that needs to be updated (ex: all Fall 2023 deposited UG applicants who have not withdrawn their deposit and do not have a current freshman or transfer cohort value)
- Know your timeline for this to occur (remember that at least 2 weeks are needed to prepare and test)
- Open a ticket with Administrative IT
- Include all of the information gathered in step 1
- Add in any supporting information
- The System Analyst will review the request to confirm that it can be done
- The System Analyst will assess the resources available to complete the request and provide an estimated timeline
- The request will be processed in a test environment
- The results will need to be reviewed by the requestor to confirm the update worked as anticipated
- Once email approval has been provided, the update will be performed in the production environment
Note: Requests to change a field with many different values should not be bulk requests. It should be completed manually by the end user.